Skip to content

Progress

The Dredgers Building Ras Malé, From Cristóbal Colón to Mahaa Jarraafu

Ras Malé is being built by ships. Giant dredgers suck sand from the seabed and pump it into the lagoon, and the arrival of bigger ones has done more than anything else to speed the project up. Here are the vessels involved and how they work.

Visit Ras Malé EditorialUpdated 20 Oct 20265 min read
Aerial view of a dredging ship connected by a floating pipeline to a new island of pumped sand at Ras Malé

Every hectare of Ras Malé started as sand on the seabed somewhere else in the atoll. Moving it is the job of dredgers, specialist ships that dig sand underwater and deliver it to the reclamation site. The size and number of dredgers working at Ras Malé has done more to shape the project's progress than any other factor. When small ones were used, progress crawled. When the big ones arrived in late 2025, it jumped. This guide explains how the ships work and which ones have been involved.

In short ⌄
  • Ras Malé is being reclaimed mainly by trailing suction hopper dredgers, ships that suck sand from the seabed, carry it to the site and pump it ashore.
  • The biggest so far is Jan De Nul's Cristóbal Colón, which carries 46,000 cubic metres per load. It took Site A from nothing to 84% in about ten weeks.
  • China Harbour's Jun Yang 1, with 21,000 cubic metres, about doubled the capacity of the earlier dredgers when it arrived in 2025.
  • The state-owned MTCC has secured a dredger three times larger than its Mahaa Jarraafu, due before the end of 2026.

How a hopper dredger works

Most of Ras Malé is being built by trailing suction hopper dredgers, or TSHDs. They work in a cycle:

  1. Dredge. The ship sails slowly over a permitted sand area, dragging one or two suction pipes along the seabed. Powerful pumps suck up a mix of sand and water.
  2. Load. The mix fills the ship's hold, called the hopper. The sand settles and excess water runs off, until the hopper is full.
  3. Sail. The loaded ship sails to the reclamation site.
  4. Discharge. The dredger connects to a floating pipeline and pumps the sand ashore, or sprays it in an arc onto the site, a technique called rainbowing.

Then it sails back and starts again, around the clock. The bigger the hopper, the more sand per trip. A dredger's capacity, measured in cubic metres per load, is the single best guide to how fast it can build land.

For Ras Malé, the Environment Protection Agency permitted dredging from two areas west of Maafushi and a third near Ithaafushi resort, with permits for enough sand to reclaim 562 hectares. Because each trip means sailing between the sand area and the lagoon, distance adds to time and fuel.

The ships

Cristóbal Colón

The largest dredger to work at Ras Malé is the Cristóbal Colón, operated by the Belgian dredging group Jan De Nul. It's a trailing suction hopper dredger with a capacity of 46,000 cubic metres per load. It arrived at the end of November 2025 and began dredging the next day for Maldives Airports Company Limited (MACL), which took on Site A.

The results were dramatic. Work at Site A began on 1 December 2025. MACL reported 41 hectares reclaimed by 24 December. By 12 February 2026, it reported 116 of Site A's 137.5 hectares, or 84.36%, done in about ten weeks. For comparison, the first contractor reclaimed 29 hectares in several months of 2024.

Jun Yang 1

China Harbour Engineering Company (CHEC) joined the project in August 2025 to reclaim Sites C and E, a total of 265 hectares. PSM News reported it was using the Jun Yang 1, a trailing suction hopper dredger with a capacity of 21,000 cubic metres, about twice the size of the vessels used earlier. By November 2025, Site C was 20.09% complete.

The earlier dredgers

Before August 2025, the work was done by smaller vessels belonging to the earlier contractors, CMC, Mohan Mutha Exports and CRCC. Their names and capacities haven't been widely published. What's clear is the pace: from the launch in December 2023 to August 2025, about 130 hectares were reclaimed in total. After the bigger dredgers arrived, the government reported nearly 500 hectares by March 2026.

Mahaa Jarraafu and MTCC's new dredger

The Mahaa Jarraafu is the trailing suction hopper dredger of the state-owned Maldives Transport and Contracting Company (MTCC). Built at Nantong Rainbow Shipyard in China, it's 92.95 metres long, can dredge at depths of up to 50 metres and has a 3,700-cubic-metre hopper. It cost about US$36 million and was due in the Maldives in October 2017. It ran aground and stopped work on 8 June 2022, and sat idle for 571 days. MTCC put the cost of that idle period at US$33 million, and said the main cause was the lack of proper maintenance schedules. It has since been repaired.

On 25 September 2026, President Mohamed Muizzu said MTCC had secured a trailing suction hopper dredger three times larger than its existing one, and hoped it would arrive before the end of 2026. He said it would speed up reclamation projects given to MTCC that hadn't yet started. He didn't name a specific project, and we haven't found confirmation of whether it will work at Ras Malé.

Why the ships matter so much

Ras Malé's history shows the link between dredger size and progress:

  • The original target, at the launch in December 2023, was to reclaim the lagoon within months. With small vessels and contract problems, only 29 hectares had been reclaimed when the first contractor left in 2024.
  • The government's November 2025 promise that reclamation would finish in March or April 2026 depended on large dredgers arriving in December.
  • When fuel prices rose in mid-2026, the President said the work slowed. Big dredgers burn large amounts of fuel on every cycle.

The dredgers belong to, or are hired by, the contractors. Our article on the contractors who have built Ras Malé covers who has done the work, and why so many have come and gone.

Ras Malé in context

The Maldives has used dredgers to make land for decades, but never on this scale. Hulhumalé's first phase, 188 hectares, took from October 1997 to June 2002 to reclaim, and its second phase added about 244 hectares from 2015. Gulhifalhu, west of Malé, was filled in a project that finished in July 2024. Ras Malé's planned 1,009 hectares is more than twice the size of both Hulhumalé phases together, and the government wants it reclaimed in about three years.

That's only possible with the world's largest class of dredgers. Ships like the Cristóbal Colón belong to international dredging groups, which move them between big port and land projects around the world. So the timing of their arrival, and how long they stay, matters a great deal to Ras Malé's schedule.

The environmental side

Dredging on this scale changes the seabed where sand is taken and the water around it. In early 2026, satellite images showed sediment plumes from the Ras Malé and Hulhumalé dredging spreading across large parts of South Malé Atoll. Dive operators and bait fishermen raised concerns, and the Environmental Regulation Authority received complaints about dredging outside permitted areas. Eagle Hills has said its waterfront project will need no further dredging. Read more in Ras Malé's environmental impact.

What to watch

  • Whether MTCC's new dredger arrives by the end of 2026, and where it's sent first.
  • How long the Cristóbal Colón stays, and whether MACL takes on more sites.
  • Updated figures for Sites C and E, where the Jun Yang 1 has been working.

For the latest site figures, see Ras Malé site by site and the progress tracker.

Questions people ask

Which dredger is building Ras Malé? ⌄
Several have worked there. The largest is Jan De Nul's Cristóbal Colón (46,000 cubic metres per load), working for MACL at Site A. China Harbour's Jun Yang 1 (21,000 cubic metres) has worked on Sites C and E.
What is a trailing suction hopper dredger? ⌄
A ship that drags suction pipes along the seabed to suck up sand, stores it in its hold (the hopper), then sails to the reclamation site and pumps the sand ashore through a pipeline.
What is the Mahaa Jarraafu? ⌄
MTCC's trailing suction hopper dredger, 92.95 metres long with a 3,700-cubic-metre hopper. In September 2026, the President said MTCC had secured a dredger three times larger, due before the end of the year.

Sources

Keep reading

The Housing Development Corporation's office building, with the HDC sign above the entrance and palm trees in front

Progress · Oct 2026

Who Pays for Ras Malé? The Cost of Building the Land

Nobody has published a full bill for Ras Malé. But the pieces are on the record: a contractor-financed plan that failed, a budget line Parliament removed, a loan through HDC whose size is secret, and a waterfront deal the government says will pay much of it back.

Aerial view of a new reclaimed island at Ras Malé with a base camp and jetty, surrounded by shallow reef and turquoise lagoon

Progress · Oct 2026

Ras Malé's Environmental Impact: Sediment, Reefs and Bait Fishing

Reclaiming a thousand hectares of lagoon changes the sea around it. Here is what has been reported about Ras Malé's effects on reefs, water quality and fishing, what's been done to limit them, and why the government calls it a climate adaptation project.

Aerial view of a contractor's base camp on reclaimed sand at Ras Malé, with site offices, containers and rows of construction machinery

Progress · Oct 2026

CMC, CRCC, CHEC and MACL: Who Has Built Ras Malé So Far

Five companies have been hired to reclaim Ras Malé in under three years, and two of them left with the work unfinished. Here is who each contractor is, which sites it took on, what it delivered and what it cost.

The Ras Malé update, once a month

Progress numbers, new guides and places that open. No spam.