Ras Malé in Numbers: Every Official Figure in One Place

Ras Malé's numbers are scattered across speeches, press releases, contracts and news reports, and they don't always agree. This page brings every published figure together, with its date and source, and flags where figures conflict.

Visit Ras Malé EditorialUpdated 20 Oct 20265 min read
Officials at the December 2023 launch of the Fushidhiggaru lagoon reclamation, standing in front of a large illustration of the planned city

Ras Malé's numbers come from many places: presidential speeches, HDC releases, contracts, parliamentary answers and news reports. They're often quoted without a date, and some of them contradict each other. This page collects the figures that have been published, each with its date and source, so you can see what's known and how it has changed. Where figures conflict, we show both. We update this page as new figures appear. For the latest progress figure on its own, see the progress tracker.

In short ⌄
  • Ras Malé's planned land is usually given as about 1,009 hectares, within a lagoon of about 1,153 hectares. The President has also said about 1,100 hectares.
  • Reclamation was about 70% complete in September 2026, according to the President, with completion targeted for the end of 2026.
  • The long-term housing target is 65,000 homes. The first round offers 15,000 plots, which drew 22,575 applications.
  • Where sources disagree, we show both figures rather than picking one.

The site

FigureValueSource and date
LagoonFushidhiggaru, about 1,153 haHDC; The Edition, Nov 2025
Lagoon (other figure)1,280 haAdhadhu, June 2024
Land to reclaimAbout 1,009 haPresident's Office, Nov 2025
Land (launch figure)1,150 haLaunch, Dec 2023
Land (latest description)About 1,100 haPresident, Sept 2026
Sites12, labelled A to LHDC and press reports
Height2 m at edges, 3 m at centrePresident's Office, Dec 2023
Distance from MaléAbout 17 minutes by speedboatLaunch reporting, Dec 2023

Why the difference? The 1,153-hectare figure is the whole lagoon, while about 1,009 hectares is the part to be turned into land. The 1,150 and 1,100 figures appear to describe the planned land in round numbers. Published site areas add up to about 1,010 hectares without Site K, whose area hasn't been published.

For scale

  • Malé island: about 1.95 km², or 195 ha. Ras Malé's planned land is about five times bigger.
  • Hulhumalé, Phases 1 and 2: about 445 ha. Ras Malé is a little over twice the size.
  • Gulhifalhu: about 150 ha, reclaimed 2020–2024. Ras Malé is more than six times bigger.

Official statements often say Ras Malé is "nearly three times" the two phases of Hulhumalé. That comparison uses the whole 1,153-hectare lagoon.

Reclamation progress

DateFigureSource
18 Dec 2023Work startsPresident's Office
202429 ha at Site J (first contractor)Adhadhu, Jan 2025
Aug 2025129.6 haMMTV; PSM
Nov 2025About 183 ha; Site J complete, L 25.53%, C 20.09%HDC; President's Office
Feb 2026Site A 116 of 137.5 ha (84.36%)MACL via MMTV
31 Mar 2026Nearly 500 ha, 11 sites activePresident, via Dredging Today
June 2026About 60%President, via Dredging Today
Sept 2026About 70%President, Nation Chat

Percentages from the President haven't come with hectare figures, and we haven't found an independent survey.

Site by site

  • Site J: 29 ha, complete (Nov 2025).
  • Site A: 137.5 ha, 84.36% (Feb 2026).
  • Sites D, F, G and L: 395 ha combined, 100.6 ha reclaimed (Aug 2025); Site L 25.53% (Nov 2025).
  • Site C: 190 ha, 20.09% (Nov 2025).
  • Site E: 75 ha, no published figure.
  • Sites B, H and I: 183.5 ha combined, no published figure.
  • Site K: area not published.

More in Ras Malé site by site.

Homes and people

FigureValueSource and date
Homes planned65,000HDC; launch plans
Plots from Ras Malé25,000 in total, 15,000 in round onePresident, Nov 2025
Plot size1,250 sq ftHousing ministry, 2026
Housing for All applications58,505 (22,575 plots, 35,930 flats)Housing ministry, June 2026
Goathigedhoru plot applications12,749 (all Ras Malé)Housing ministry, June 2026
Land for housingAbout 500 haGovernment statement, Sept 2026
Land for housing plots (other figure)About 600 haPresident, Sept 2026
Residents (housing land)150,000+Government, Sept 2026
Residents (master plan goal)300,000+ within 20 yearsMaster plan brief, Oct 2025
China housing MoU30,000 unitsHousing minister, Jan 2024

More in housing in Ras Malé.

Contractors and costs

  • Launch budget: MVR 1.4 billion over three years, including MVR 400 million for 2024, which Parliament removed (Dec 2023 to Mar 2024).
  • Minister's estimate: at least US$500 million to US$700 million to reclaim about 1,100 ha (2024).
  • CMC: 29 ha; settlement of US$21 million (Jan 2025).
  • CRCC: US$265.5 million contract for 352 ha in 18 months (July 2024); ended July 2025; US$13.2 million advance; US$9.4 million claim accepted, against a US$6.7 million valuation (Aug 2026).
  • CHEC: Sites C and E, 265 ha (Aug 2025).
  • MACL: Site A, 137.5 ha (from Dec 2025).
  • HDC loan: amount and lender not disclosed.

More in who pays for Ras Malé.

Money for buyers and builders

  • BML home construction loans: 5% equity for projects up to MVR 3 million, 20% above (from April 2026).
  • Hiyaavehi construction loans: 5% a year, up to 25 years, including an 18-month grace period. Caps are MVR 1 million on the atolls, MVR 3 million in cities and MVR 6 million in the Malé area (from 2025).
  • Corporate resident visa: US$250,000 investment or five-year deposit, valid five years, MVR 15,000 fee.
  • Leases for foreign buyers: up to 99 years, with a 4% fee on each transfer (Eagle Hills terms).

The ships

  • Cristóbal Colón (Jan De Nul, for MACL): 46,000 m³ per load.
  • Jun Yang 1 (CHEC): 21,000 m³ per load.
  • MTCC: a dredger three times the size of its 3,700 m³ Mahaa Jarraafu, due by the end of 2026.

The environment

  • Corals relocated: 21,641 (2025).
  • Sand permits: two areas west of Maafushi and one near Ithaafushi, enough for 562 ha, six-month permits.

The Eagle Hills deal

FigureValueSource and date
Signed21 Sept 2026 (commercial terms)Gulf News
LandAbout 500 haGovernment, Sept 2026
ValueUS$12 billion (reported); up to US$20 billionReuters, Bloomberg; government
PropertiesMore than 8,800Maldives Independent, Oct 2026
LeasesUp to 99 yearsGovernment
State share10% of first-sale revenue, about US$3.1 bn over 10 yearsHousing minister, Oct 2026
Transfer fee4% of property valueGovernment
State revenue (projected)More than US$11 billionGovernment
Jobs (projected)More than 54,000Government
Hulhumalé homes5,000, about US$500 millionGovernment

Timelines

  • Reclamation target: end of 2026 (Sept 2026). Earlier targets: within months of launch (2023), March–April 2026 (Nov 2025), early 2026 (Dec 2025).
  • Wider city: about 10 years (Sept 2026).
  • Master plan: final plan due June 2026 under the brief; not published as of Oct 2026.
  • Transport master plan: expressions of interest closed 31 Dec 2025; no award found.
  • Speedboat from Malé: about 17 minutes (launch reporting, Dec 2023).
  • Undersea tunnel: announced by the President in January 2024, with feasibility work said to be under way. No route or cost published.
  • Transport master plan: project TES/2025/C-007, put out to consultants in December 2025.
  • Airstrip: planned near the lagoon, according to HDC. No construction announced.

Using these figures

If you quote a Ras Malé figure, quote its date and source too, because many have changed several times. When you see a figure without a date, check it against this page. Spot one we've missed, or a newer one? Tell us, and we'll add it.

Questions people ask

How big is Ras Malé? ⌄
The planned land is usually given as about 1,009 hectares, within a lagoon of about 1,153 hectares. In September 2026, the President described it as about 1,100 hectares.
How much of Ras Malé has been reclaimed? ⌄
About 70%, according to the President in September 2026. Nearly 500 hectares had been reclaimed by March 2026.
How many homes will Ras Malé have? ⌄
The long-term target is 65,000 homes. The first Housing for All round offers 15,000 plots, and the President has said 25,000 plots will come from Ras Malé in total.

Sources

Keep reading

Artist's impression from above of a planned waterfront district with rows of homes, gardens, sports courts and a beach

Guides & FAQ · Oct 2026

A Ras Malé Glossary: From Falhu to Hiyaavehi

Ras Malé news mixes Dhivehi place names, housing-scheme titles, engineering jargon and property law. This glossary explains the terms you're most likely to meet, in plain English, with links to where we cover each one.

Officials and engineers in hard hats and high-visibility vests studying plans spread out on a table at a construction site

Guides & FAQ · Oct 2026

Who's Who in Ras Malé: The Agencies and Companies Involved

Dozens of organisations have a hand in Ras Malé: ministries, state companies, foreign contractors, a Gulf developer, banks, regulators and courts. Here is who they are and what each does, so the news makes more sense.

Newly reclaimed sand being shaped by machinery in a turquoise lagoon, with a city skyline on the horizon

Guides & FAQ · Oct 2026

A Short History of Reclaimed Land in Greater Malé