Reclamation Around Malé in 2026: Every Project Under Way

Ras Malé is the biggest, but it isn't the only new land being made around the capital. In 2026, giant dredgers have also been working at Hulhumalé and Giraavarufalhu. Here is every project, who is doing it, and what the land is for.

Visit Ras Malé EditorialUpdated 9 Nov 20266 min read
Dredgers and newly reclaimed land in the Greater Malé area

Ras Malé gets most of the attention, but it isn't the only new land being made around the capital. In 2026, some of the world's largest dredgers have been working at several sites in Greater Malé at once, adding hundreds of hectares to a region that has run out of room. This guide brings every project together: where it is, who is doing it, how far it has got and what the land is for.

In short ⌄
  • Ras Malé is about 70% reclaimed (September 2026) and is by far the largest project, at about 1,009 to 1,150 hectares.
  • Hulhumalé Phase 3, 63 hectares, was declared complete in January 2026. Giraavarufalhu, about 167 hectares, was about 105 hectares complete by late March 2026.
  • Gulhifalhu, about 150 hectares, was finished in 2024 and is waiting for the Thilamalé Bridge. Thilafushi is to host Malé's new commercial port.
  • The state-owned airports company MACL has become one of the country's main reclamation contractors, working at Ras Malé, Hulhumalé and Giraavarufalhu.

For the long view, from the airport runway in the 1960s onwards, see a short history of reclaimed land in Greater Malé.

At a glance

  • Ras Malé: about 1,009 to 1,150 hectares; about 70% reclaimed; housing and the Eagle Hills waterfront.
  • Hulhumalé Phase 3: 63 hectares; declared complete in January 2026; housing plots.
  • Giraavarufalhu: about 167 hectares; about 105 hectares done by late March 2026; housing plots.
  • Gulhifalhu: about 150 hectares; finished in 2024; housing and industry, waiting for the bridge.
  • Thilafushi: existing industrial island; planned site of the new commercial port.

Together, the four new areas have added, or are adding, roughly 1,400 to 1,500 hectares of land around the capital, depending on which figure you use for Ras Malé. That is about seven to eight times the area of Malé island itself, which covers about 195 hectares.

Why so much reclamation, all at once?

The government's answer is housing. Malé island covers about 1.95 square kilometres and had more than 211,000 people in its administrative area at the 2022 census. Thousands of families are waiting for land or flats, and when Housing for All applications closed in June 2026, there were 58,505 applications. Reclamation is the only way to create land near the capital on that scale.

The government also describes the new land as climate adaptation, because it can be built higher than natural islands. See our guide to sea level rise and the Maldives.

Ras Malé (Fushidhiggaru)

  • Where: Fushidhiggaru lagoon, south of Malé in South Malé Atoll, near Gulhi.
  • Size: about 1,009 hectares of planned land, by most HDC figures, or about 1,100 to 1,150 hectares in other official statements.
  • Progress: about 70%, according to the President in September 2026, with the rest due by the end of 2026.
  • Who: HDC is the client. Contractors have included CMC, Mohan Mutha Exports, CRCC (until July 2025), China Harbour Engineering Company (CHEC) and MACL.
  • For: housing under Housing for All, a long-term target of 65,000 homes, and the Eagle Hills waterfront and marina on about 500 hectares.

See our progress tracker, Ras Malé site by site and why the progress figures differ.

Hulhumalé Phase 3

  • Where: an extension of Hulhumalé, the reclaimed city next to the airport.
  • Size: 63 hectares.
  • Progress: work resumed in November 2025, after earlier delays. By 10 November, 24 hectares had been reclaimed. In January 2026, MACL reported 87% overall progress with 55 hectares reclaimed, and in late January 2026 the President announced, at a ruling party event, that the reclamation was complete and land handover was under way. The project had begun in September 2023 and stalled after the change of government, before resuming.
  • Who: reports name different lead companies. The President's Office said in November 2025 that the contractor was CMC, using a 22,000-cubic-metre dredger supplied by Boskalis. In January 2026, the Maldives Standard reported that MACL was leading the works, with the dredgers Prins der Nederlanden and Oranje, each of about 22,000 cubic metres.
  • For: housing plots. Around 1,351 plots have been earmarked there, many for people allocated land under the previous government's Binveriya scheme.

Hulhumalé's revised master plan of May 2025 also proposed reclaiming the water strip between Phases 2 and 3 to join them, and expanding the harbour from 36 to 53 hectares.

Giraavarufalhu

  • Where: Giraavaru lagoon, west of Malé near Thilafushi, in the Greater Malé area.
  • Size: about 167 hectares in two phases. The housing minister has also given the goal as 169 hectares.
  • Progress: the first phase, 70 hectares, was reclaimed earlier, under a project started by the previous government that stalled. The government then handed the second phase, 97.15 hectares, to MACL, which began on 30 January 2026. By late March 2026, about 105 hectares of the total had been completed. The President had said reclamation and plot surveys would finish by the end of April, with plot handovers starting in June. A June update to Parliament gave a lower figure of 98 hectares, showing how progress figures can differ.
  • Who: MACL, with the dredgers Queen of the Netherlands, about 35,000 cubic metres, and Oranje, about 22,000 cubic metres.
  • For: housing. Reports have said about 4,072 plots in four sizes will be allocated there. Some plots originally planned for Giraavarufalhu were moved to Gulhifalhu.

Gulhifalhu

  • Where: between Villimalé and Thilafushi, about 6 kilometres from central Malé.
  • Size: about 150 hectares.
  • Progress: finished in July 2024, by Boskalis.
  • For: originally a new commercial port, which the government moved to Thilafushi in 2024. More than 3,500 housing plots have since been assigned there, to be handed over once the Thilamalé Bridge is complete, now targeted for the end of 2027.

See our guide to Gulhifalhu.

Thilafushi

Thilafushi, the capital's industrial and landfill island, isn't a new reclamation in the same way, but it is changing fast. It is the planned site of the Greater Malé commercial port, financed largely through an Indian line of credit, and it will be on the route of the Thilamalé Bridge. A second reclaimed area, Thilafushi-2, has already been made for heavy industry.

What's next: Uthuru Thilafalhu and beyond

The list is still growing. When he announced the end of Hulhumalé Phase 3, the President said further reclamation was planned at Uthuru Thilafalhu, north of Malé. Hulhumalé's own plan includes joining Phases 2 and 3. And MTCC's new, larger dredger is meant to speed up projects on other islands. The government has said it wants to create land wherever housing is short, which means reclamation is likely to remain a feature of life in Greater Malé for years.

The ships doing the work

The pace of reclamation around Malé depends on the size of the ships, and 2025 and 2026 brought some of the biggest in the world:

  • Cristóbal Colón (Jan De Nul): about 46,000 cubic metres. At Ras Malé Site A for MACL since 1 December 2025.
  • Queen of the Netherlands: about 35,000 cubic metres. At Giraavarufalhu from early 2026.
  • Prins der Nederlanden and Oranje: about 22,000 cubic metres each. Reported at Hulhumalé Phase 3, and Oranje at Giraavarufalhu.
  • Jun Yang 1 (China Harbour): about 21,000 cubic metres. At Ras Malé Sites C and E since August 2025.

The state-owned MTCC is also getting a bigger ship. In September 2026, the President said a dredger three times larger than MTCC's existing vessel was expected to arrive before the end of 2026, to speed up reclamation projects assigned to MTCC. Our guide to the dredgers building Ras Malé explains how these ships work.

MACL: the airports company that reclaims land

One of the most striking changes of the past year is the role of Maldives Airports Company Limited (MACL), the state company that runs Velana International Airport. Since late 2025, it has become one of the government's main reclamation contractors: at Ras Malé Site A, at Giraavarufalhu's second phase, and, by some reports, at Hulhumalé Phase 3. Giving work to a state company with access to very large hired dredgers has been faster than relying on some of the private contractors who struggled in 2024 and 2025. It also puts more of the cost and risk on the state.

The environmental cost

So much dredging in one region at the same time has consequences. In early 2026, satellite images showed sediment plumes across large parts of South Malé Atoll, and dive operators reported murkier water and fewer sharks at popular sites near Hulhumalé. Fishermen have asked the state to stop taking sand from prime bait fishing grounds. In December 2025, the Environmental Regulation Authority said it had received complaints about dredging outside permitted areas. See our report on Ras Malé's environmental impact.

What to watch

  • Ras Malé's finish. Whether reclamation is completed by the end of 2026, as promised.
  • Plot handovers. Hulhumalé Phase 3 and Giraavarufalhu are meant to deliver plots before Ras Malé does. Delays there would be a warning sign.
  • The bridge. Gulhifalhu, Giraavarufalhu and Thilafushi all depend on the Thilamalé Bridge for road access.
  • MTCC's new dredger, and which projects it is assigned to.

Questions people ask

What land reclamation is happening around Malé? ⌄
In 2026, the main projects are Ras Malé, Hulhumalé Phase 3 and Giraavarufalhu. Gulhifalhu was finished in 2024, and Thilafushi is being developed as the site of Malé's new port.
Is Hulhumalé Phase 3 finished? ⌄
The President announced in late January 2026 that the 63-hectare reclamation was complete and land handover was under way.
Who is reclaiming land around Malé? ⌄
The state-owned airports company MACL has become one of the main contractors, alongside China Harbour, Mohan Mutha Exports, CMC and the state company MTCC, using large dredgers hired from companies such as Jan De Nul and Boskalis.

Sources

Keep reading

A large trailing suction hopper dredger working off the reclaimed land at Ras Malé

Progress · Nov 2026

Ras Malé in 2025: The Year Reclamation Sped Up

Ras Malé started 2025 with about 100 hectares of land and a contract heading for the rocks. It ended the year with new contractors, the biggest dredger in the country and a housing policy built around it. Here is what happened, month by month.

Sand being pumped onto reclaimed land at Ras Malé

Progress · Nov 2026

Why Ras Malé's Progress Figures Don't Always Agree

In the same month, Ras Malé was reported as 43% and about 60% reclaimed. Neither figure was necessarily wrong. Here is why progress numbers differ, from different totals to site-level percentages, and how to read the next one you see.